Artemis II Wet Dress Rehearsal: Taking Things Into the Home Stretch

In the pre-rocket-launch preparation ritual known as the wet dress rehearsal (WDR), the Artemis II launch team runs through nearly every step of the countdown sequence just as they would on launch day. The only things missing: the astronauts themselves and actual rocket ignition.

For NASA’s Space Launch System (SLS) launch vehicle, this means loading nearly 750,000 gallons of liquid hydrogen and liquid oxygen into the core stage tanks, verifying that the four RS-25 main engines are functioning properly and bringing them to the so-called “start box” – the precise range of temperature and pressure conditions required for ignition. At the same time, engineers check that the engines are communicating correctly with the vehicle and spin up the core stage auxiliary power units (APUs), which power the actuators that move the engine nozzles to steer the vehicle during launch.

Artemis roll out

NASA’s Artemis II Space Launch System (SLS) rocket and Orion spacecraft are seen illuminated by lights at Launch Complex 39B at NASA’s Kennedy Space Center in Florida. Credit: NASA

I’m excited to play a role in returning humans back to the lunar vicinity for the first time in 50 years. Every test, every rehearsal, brings us one step closer to making history again.
- Bill Muddle, Lead RS-25 Field Engineer, L3Harris

“Completing WDR is a major step to validate all the systems on the Artemis II stack, including the RS-25 engines,” says Bill Muddle, Lead RS-25 Field Engineer, L3Harris. “The WDR is the final ‘test like you fly’ exercise, validating that all systems are working properly and ready to go for launch.”

The WDR will take place ahead of the upcoming Artemis II mission, which is the first astronaut-carrying flight of the SLS and Orion spacecraft. The mission will take its four-person crew on a journey around the far side of the moon and back in preparation for a return of astronauts to the lunar surface in the coming years.

For the launch and WDR, the teams will be in place well before the fuel starts flowing in earnest. At T-19 hours, for example, the engine controllers are powered up to perform a few additional checkouts to make sure they are working properly.

Once the systems are verified, the teams move on to a series of four purges, the first two of which use heated nitrogen gas to flush any moisture that might have built up in the engines and associated plumbing. This ensures they operate effectively and safely throughout the mission. Purge 3 begins a slow flow of liquid hydrogen and liquid oxygen from the ground spherical tanks to the engines, effectively beginning the chill-down process.

“We chill down the lines from the spheres, then we start chilling the vehicle,” Muddle says.  “The fueling is done in phases, starting off slowly to fill the lower part of the core stage propellant tanks. The launch team then opens the spigots for fast fill, during which the fuel flows at a rate of about 1,300 gallons per minute for liquid oxygen and about 8,000 gallons per minute for liquid hydrogen.”

Once the tanks are nearly full, the flow is slowed once more until they reach what is called “stable replenishment,” at which point the tanks are topped off to keep pace with the loss of the cryogenic propellants due to boiloff. Loading of the SLS second stage, or Interim Cryogenic Propulsion Stage, begins at a point when the core stage is partially loaded, so that both stages reach stable replenishment at approximately the same time.

“Orchestrating the propellant filling process so that all four tanks reach stable replenishment requires some real rocket science,” Muddle adds. “Data gleaned from the WDR will be used to make any necessary adjustments prior to launch.”

At T-3 minutes and 50 seconds, the core stage APUs are started, paving the way for the fourth purge sequence when the RS-25 engines change from pneumatic to hydraulic control for flight.

The WDR takes the countdown all the way to T-30 seconds when control of the vehicle transitions from the ground launch sequencer to the automated launch sequencer, stopping just shy of the T-6 second mark when the engines would light one by one during an actual launch.

From his vantage point in the Launch Control Center’s Firing Room 4, Muddle will be in the thick of the action during the WDR and the actual launch. 

“I’m excited to play a role in returning humans back to the lunar vicinity for the first time in 50 years,” said Muddle. “Every test, every rehearsal, brings us one step closer to making history again.”

Featured News

Screenshot of re-entry mission

Editorial | 04. 14. 2026

Supporting Safe Space Flights with WESCAM MX-Series Imaging Systems

WESCAM MX™-Series EO/IR Systems Provide Critical Visibility During NASA Re-Entry Operations.

Screenshot of re-entry mission

Editorial | 04. 14. 2026

Supporting Safe Space Flights with WESCAM MX-Series Imaging Systems

L3Harris is designing and building 18 infrared space vehicles for the Space Development Agency’s Tranche 2 Tracking Layer program that will provide near-global missile warning and tracking coverage.

Editorial | 04. 13. 2026

When Missiles Move at 5X the Speed of Sound, Timing Is Everything

3D printed RL10 rocket engine combustion chambers shown in the manufacturing area at L3Harris’ facility in West Palm Beach, Florida.

Editorial | 04. 10. 2026

Accelerating Production of National Security Space Assets with Additive Manufacturing

Artemis II launches from earth

Press release | 04. 01. 2026

L3Harris Powers First Crewed Mission Around the Moon in 50 Years

An auxiliary target has been affixed to the Interim Cryogenic Propulsion Stage

Editorial | 03. 23. 2026

RL10 and Orion Main Engine are Key to NASA’s Historic Artemis II Journey to the Moon